Tony
Alligator Snapping Turtle/Past Pres
From the auction thread:
These are pictures I took last week at the new National Fire Lab on the NIST campus in Gaithersburg. It was about an 800 cubic yard pour on an 4 foot thick elevated deck (!). The pour started at 4:00 AM and we were poured out around 9:00 or so. We used two 42 meter concrete pumps which were fed almost continuously by two ready-mix trucks at a time.
The grid on top of the slab was to hold the 1200 galvanized sleeves in place. The tolerance for placement of the sleeves is under 1/32" in any direction (X/Y/Z). Each sleeve weighs approximately 90 pounds. This is in addition to the 1900 tons of wet concrete and 160 tons of rebar (again - all in an elevated deck 10 feet off the 3' thick foundation mat).
Beyond the reinforcing steel, running through the middle of the slab are 27 runs of bonded 6-strand post-tension cable (approximately 2,100 LF of tendon or about 2.5 miles of individual strand). After placement and curing of the concrete, the tendons are individually stressed with a hydraulic ram to carry 257,000 pounds of tension each.
Tis glorious, no?
I love my job. It's like playing with giant Legos.
Not the biggest pour I've ever done on one of my jobs, but certainly the most complex.
Judging by the exalted nature of his response I'd speculate that he's lost in another reverie about the glories of things concrete.
These are pictures I took last week at the new National Fire Lab on the NIST campus in Gaithersburg. It was about an 800 cubic yard pour on an 4 foot thick elevated deck (!). The pour started at 4:00 AM and we were poured out around 9:00 or so. We used two 42 meter concrete pumps which were fed almost continuously by two ready-mix trucks at a time.
The grid on top of the slab was to hold the 1200 galvanized sleeves in place. The tolerance for placement of the sleeves is under 1/32" in any direction (X/Y/Z). Each sleeve weighs approximately 90 pounds. This is in addition to the 1900 tons of wet concrete and 160 tons of rebar (again - all in an elevated deck 10 feet off the 3' thick foundation mat).
Beyond the reinforcing steel, running through the middle of the slab are 27 runs of bonded 6-strand post-tension cable (approximately 2,100 LF of tendon or about 2.5 miles of individual strand). After placement and curing of the concrete, the tendons are individually stressed with a hydraulic ram to carry 257,000 pounds of tension each.
Tis glorious, no?
I love my job. It's like playing with giant Legos.
Not the biggest pour I've ever done on one of my jobs, but certainly the most complex.